| Jamuna
Bridge Railway Link Project, Contract No. 1 |
| |
Samwhan performed
Jamuna Bridge Railway Link Project, Contract No. 1 from
December 1997
to December 2002.
This Project includes the construction of 99 km-long railway,
63 bridges, 94 box culverts, etc.
Total constructon cost was US$ 118 million. |
|
Jamuna
Multipurpose Bridge Project, Contract Nos. 3 & 4,
East & West Road Approaches |
| |
The East Roal Approach,
the top, and the West Road Approach, the below.
Total length of the road is 32.54 km with the width of 12.2m.
Construction cost was US$ 57 million.
The Projects were commenced in October 1994 and completed
in October 1997 for West Road
Approach and February 1998 for East Road Approach. |
|
| Road
Rehabilitation & Maintenance Project, North/West Bangladesh
Contract RRMP(NW) 1/4, 1/5 & 1/6, Bogra ~ Lanpur Highway |
Samwhan's first highway
project in
Bangladesh.
This is a 12.2 m-wide (2 lane) and
65 km-long highway linking Mohasthan
and Pirgang in northwest Bangladesh.
The project was started in 1988 and
completed in 1991.
Its client is Roads and Highways
Department(RHD), Ministry of
Communications, Bangladesh. |
 |
|
|
| Korean
Embassy in Bangladesh |
 |
Samwhan commenced
the construction of New Korean Embassy in Dhaka, Bangladesh
in December 1996 and completed it in March 1998.
This diplomatic compound is a 2-story building with 1-story
basement.
Total floor area is 3,037 §³. |

|