| Hussein
Thermal Power Station |
| |
Hussein
Thermal Power Station, Stage III and IV Works included furnishing,
delivering,
erecting, testing and intial operating of equipment, machinery
and accessories for
Unit No. IV, V, VI and VII of Hussein Thermal Power Station
which is located in Amman,
Jordan. The project was commenced in February 1980 and completed
in January 1985.
The client was Jordan Electricity Authority. |
|
| 15§Ó
Steam & Power Plant |
 |
This 15 MW Steam & Power Plant,
owned
by Arab Potash Company Ltd.
was completed in July, 1981.
The plant is located at Safi, Jordan.
- Boiler : 2 units
Capacity : 110 ton/hr
- Turbine : 1 unit
Capacity : 15 MW
- Fuel Oil System |
|
This chancellery
and 15 other buildings are of peculiar Yemen style.
It has a total floor area of 5,868 §³. |
|
| New
Korean Embassy in Jordan |
This embassy was built with RC &
Brick structure.
Total floor area is 3,542 §³.
Construction period was from
February 1985 to November 1986. |
 |
|
|
| Queen
Alia Hopital |
| |
| 150-bed Hospital
Building, Doctor's Office Building and Nurses' Residence
Building of R.C./
Rahmen Structure with the total floor area of 19,260 §³
were constructed in Amman, Jordan.
Construction work was commenced in 1982 and completed
in 1984. |
|
| |

|