| Name
of Project
(Location) |
Owner/Clint |
Period of
Work |
Scope Work |
Vietnam Three Cities
Sanition Project,
Haiphong Sub-Project,
Contract No. HPSANP-C1C
(Vietnam) |
Haiphong Sewerage and
Drainage Company(SADCo)
Haiphong Sewerage
and sanitation
Projects Management
Unit(PMU)
|
Mar. 02, 02
Mar. 01, 05 |
Construction of Sludge and
Septage Treatment, Disposal
Facilities & ComPosting Plant
4 Regulation Lakes : 11.5 ha
Dredging : 64,600§©
Drainage Channels : 6.2km
Combined Sewers : 7.6km
Access Road : 6km
Rehabilitation of Tidal Gates |
National Highway No. 1
Bridge Rehabilitation Project,
Phase II-3, Package 1 :
New Construction of Cau
Lau Bridge
(Vietnam) |
No. 18 Projects
Management unit,
Ministry of Transport
and Communications |
Jul. 01, 01
Jun. 30, 03 |
Construction of a Cantilever Bridge of 1,056m
x 14m with
PC Box Girder including
3.6km access road. |
National Highway No. 18
Improvement Project,
Pakage 2 : Section Bac
Ninh to Chi Linh
(Vietnam)
|
No. 18 Projects
Management unit,
Ministry of Transport
and Communications |
Jul. 01, 00
Mar. 31, 03 |
Expansion & Widenung of 29.6
km existing road 7~8m wide to the width of 15m including
7 bridges(total length : 276m)
Embankment : 809,553§©,
Asphalt Concrete Pavement
127,000 ton. |
National Highway No. 1
Bridge Rehabilitation Project
(Vitenam) |
No. 18 Projects
Management unit,
Ministry of Transport
and Communications |
Aug. 15, 96
Jan. 31, 01 |
Reconstruction/Rehabilitation of
25 Bridges.
TOtal Length : 959.9m,
Access Road : 7,299m,
Embankment : 343,000§©,
1 Box Culvert : 20m. |
Champassak
Road Improvement
Project, Contract c :
Phiafay ~ Nasenphan
(Lao, PDR) |
Ministry of Communi-
cation, Transport,
Post & Construction |
May 31, 96
Jun. 30, 00 |
Total Length : 66km,
DBST pavement & 14 P.C.
Girder Bridges. |
Second Road Rehabili-
tation and Maintenance
Project, Contract No. 4,
Rajshahi~Nawabgonj
Section
(Bangladesh)
|
Roads and Highways
Dep't., Ministry of
COmmunication |
Sep. 24, 95
Sep. 23, 98 |
Total Length : 49.9km,
Width : 12.2km,
Excavation : 20,500§©,
Embankment : 1,115,033§©,
Ascon Pavement : 35,5000 ton.
|
Feeder Roads Improvement Project,
Contracts 6, 7 & 8
(Bangladesh) |
Roads and Hghway
Dep't., Ministry of
Communications |
Nov. 01, 90
Oct. 31, 93 |
Rehabilitation and Reconstruction.
Total Length : 89km,
Width : 7m. |
Contract No.
TC 120-45-812, Upgrading & Sealing of
N9 Coastal Highway,
Wariman to Hawain River
(Papua New Guinea) |
The Secretary
Department of Works,
Papua New Guinea |
Jul. 30, 90
May 31, 91 |
Total Length : 25.5km,
Width : 7m. |
Upgrading of the Northern
Highway from Buna Road
Junction to Beamu Creek
Bridge in Northern Province, Contract No.
TC 20-36-414
(Papua New Guinea) |
The Secretary
Department of Works
apua New Guinea |
Aug. 18, 86
Jun. 14, 88 |
Total Length : 28.5km,
Width : 9.5m,
Excavation : 19,450§©,
Embankment : 41,000§©,
DBST : 200,000§©. |
Additional Pipeline and
Recirculation System,
JP-4, Storage Facilities
(Hodeidah, Republic of
Yemen) |
General Petroleum
& Mineral Organiza_
tion(PETROMIN) |
Aug. 19, 85
Apr. 18, 86 |
Mech. Works
- Submarine Pipeline : 1.3km
- Recirculation Pump : 1 unit
- Injection Pump : 1 unit
Elec. Works
- Cathodic Protection System : 1L/S |
|

|